Infrastructure Projects

Infrastructure Projects

Precinct 3 proudly brings you road, bridge and park projects that are managed by a team of licensed professional engineers, each with vast knowledge and experience on Harris County infrastructure. You can rest assured that each project and community have been studied to deliver the highest of quality and safety from design and into construction. Please see the list below for projects that are currently in design and construction. For questions or comments, click here.

Projects in Construction

Asphalt Reconstruction 2024-3

Project Scope: Roadway improvements to Root Road, Dowdell Road, Kuykendahl Road

Benefits: Increasing safety and mobility throughout these areas

Phase: Construction

Est. Construction Cost: $5 million

Est. Construction Completion: Fourth Quarter of 2025

Asphalt Reconstruction Package 2022-2, Humble and Crosby areas

Project Scope: Reconstruct various roads in Humble and Crosby, roadway portions include Aldine Westfield Road, First Street in the Crosby area, Miller Wilson Road, Hare Cook Road, Ramsey Road, East Stroker Road, and Krenek Road

Benefits: Increase safety and mobility throughout these areas

Phase: Construction

Est. Construction Cost: $11.3 million

Est. Construction Completion: Second Quarter of 2024

Baldwin Boettcher Library Mitigation

Project Scope: Reconstruct the building from 2017 hurricane damages

Benefits: Building library to its original layout

Phase: Construction

Est. Construction Cost: $2.8 million

Est. Construction Completion: Third Quarter of 2024

Barrett Station, Barrett Settlement and St. Charles Place

Project Scope: Upgrading culverts with driveway replacements, regrading ditches and constructing a detention basin

Benefits: Improved drainage

Phase: Construction

Est. Construction Cost: $11.6 million

Est. Construction Completion: Second Quarter of 2025

Barrett Station, Dreamland Place

Project Scope: Upgrading culverts with driveway replacements, completing unfinished roads to join multiple sections of neighborhood, regrading ditches and constructing a detention basin

Benefits: Improved Drainage

Phase: Construction

Est. Construction Cost: $6 million

Est. Construction Completion: Fourth Quarter of 2024

Bernadine Estates and Tower Oaks Subdivisions

Project Scope: Subdivision drainage improvements through storm sewer installation, a large detention basin, culvert replacements, ditch regrading, and pavement reconstruction

Benefits: Improved safety and increased efficiency for drainage

Phase: Construction

Est. Construction Cost: $18.9 million

Est. Construction Completion: Fourth Quarter of 2024

Crosby Township/MUD (Runneburg)

Project Scope: Subdivision drainage improvements and channel excavation

Benefits: Increased drainage capacity and reduced flood risk

Phase: Construction

Est. Construction Cost: $2.3 million

Est. Construction Completion: Fourth Quarter of 2024

Cumberland Ridge at Fairfield Place Traffic Signal

Project Scope: Installation of new mast arm traffic signal

Benefits: Improve driver safety

Phase: Construction

Est. Construction Cost: 500,000

Est. Construction Completion: Fourth Quarter of 2024

Cypress North Houston Road at Barker Trace Drive Traffic Signal

Project Scope: Installation of new mast arm traffic signal

Benefits: Improve driver safety

Phase: Construction

Est. Construction Cost: $418,114

Est. Construction Completion: Fourth Quarter of 2024

Cypress North Houston at Barker Trace

Project Scope: Install new traffic signal

Benefits: Improve driver safety

Phase: Construction

Est. Construction Cost: $390,000

Est. Construction Completion: Third Quarter of 2024

Detention Pond Enhancement - Cypress Park

Project Scope: Installing gravity flow pump as part of pilot program

Benefits: Improving water flow from pond to nearby watershed

Phase: Construction

Est. Construction Cost: $6.5 million

Est. Construction Completion: Third Quarter of 2025

Detention Pond Enhancement - Goforth Park

Project Scope: Detention pond pilot program - pump flow

Benefits: Will lower pond water level before storm to increase storm water detention volume

Phase: Construction

Est. Construction Cost: $3.5 million

Est. Construction Completion: Fourth Quarter of 2025

Dula Lane Reconstruction

Project Scope: Roadway drainage improvements and pavement reconstruction

Benefits: Increased drainage capacity, reduced flood risk, and reduced long-term maintenance costs

Phase: Construction

Est. Construction Cost: $1.6 million

Est. Construction Completion: First Quarter of 2025

Fairfield Place at Fairfield Green Drive

Project Scope: Install pedestrian flashing signs

Benefits: Improve pedestrian safety

Phase: Construction

Est. Construction Cost: $40,000

Est. Construction Completion: Second Quarter of 2024

Fry Road at Mound Road/Cypress North Houston at Barker Cypress Road

Project Scope: Intersection improvements

Benefits: Improve driver safety

Phase: Construction

Est. Construction Cost: $380,000

Est. Construction Completion: Second Quarter of 2025

Greenhouse Road Bridge over Cypress Creek

Project Scope: Construct the northbound 2-lane bridge over Cypress Creek

Benefits: Improved safety, increased capacity for vehicular travel, and added safety and capacity for pedestrian mobility

Phase: Construction

Est. Construction Cost: $8.2 million

Est. Construction Completion: Second Quarter of 2025

Huffmeister Road Sidewalk from Fleur de Lis Blvd to north of Cypress North Houston Road

Project Scope: Construct a 5’-wide sidewalk on both the east and west sides of Huffmeister Road

Benefits: Includes safer pedestrian access

Phase: Construction

Est. Construction Cost: $355,965

Est. Construction Completion: Third Quarter of 2024

Hufsmith-Kohrville Road, Segment 2

Project Scope: Reconstruct from a 2-lane asphalt roadway to a 4-lane concrete blvd with storm sewer and sidewalk from south of Rolling Glen Ln to north of Ezekiel Rd

Benefits: Improved safety, increased capacity for vehicular travel, added safety and capacity for pedestrian mobility, and increased efficiency for drainage

Phase: Construction

Est. Construction Cost: $12.5 million

Est. Construction Completion: First Quarter of 2025

Lindsay Lyons Parking Lot Improvements

Project Scope: Parking lot improvements

Benefits: Park enhancements

Phase: Construction

Est. Construction Cost: $400,000

Est. Construction Completion: First Quarter of 2025

Madera Run Parkway from Radura Road to Hickory Arroyo Drive

Project Scope: Construct the remaining 2 lanes of a 4-lane concrete boulevard through a partnership with Harris County MUD 504

Benefits: Improved safety and increased capacity for vehicular travel

Phase: Construction

Est. Construction Cost: $1.2 million

Est. Construction Completion: Third Quarter of 2024

Mound Road Extension, Phase 1

Project Scope: Construct Mound Road from Greenhouse Road to 850 feet east of Greenhouse Road

Benefits: Added capacity, improved drainage, and connectivity from Greenhouse Road

Phase: Construction

Est. Construction Cost: $1 million

Est. Construction Completion: Fourth Quarter of 2024

Mound Road Extension Phase II

Project Scope: Construct Mound Rd from 850' east of Greenhouse Rd to the Hot Wells shooting range

Benefits: Added capacity, improved drainage, and connectivity from Greenhouse Rd

Phase: Construction

Est. Construction Cost: $2.2 million

Est. Construction Completion: Second Quarter of 2025

Pickleball Courts - IT May Park

Project Scope: Construction of outdoor pickleball courts

Benefits: Enhances park experience by providing additional recreational amenities

Phase: Construction

Est. Construction Cost: $100,000

Est. Construction Completion: Fourth Quarter of 2024

Pickleball Courts - Meyer Park

Project Scope: Construction of outdoor pickleball courts

Benefits: Enhances park experience by providing additional recreational amenities

Phase: Construction

Est. Construction Cost: $100,000

Est. Construction Completion: Fourth Quarter of 2024

Pickleball Courts - Russ Poppe Family Park

Project Scope: Construction of outdoor pickleball courts

Benefits: Enhances park experience by providing additional recreational amenities

Phase: Construction

Est. Construction Cost: $100,000

Est. Construction Completion: Fourth Quarter of 2024

Prado Woods

Project Scope: Subdivision drainage improvements through roadway reconstruction and storm sewer installation

Benefits: Increased drainage capacity, reduced flood risk, and safer travel

Phase: Construction

Est. Construction Cost: $2.1 million

Est. Construction Completion: Fourth Quarter of 2024

Schiel Road Segment 2 from west of Fairfield Place Drive to west of Mason Drive

Project Scope: Convert 2-lane asphalt with roadside ditch to a 4-lane concrete boulevard with raised median and underground storm sewer

Benefits: Increased capacity for traffic volume, a safer roadway, and improved drainage

Phase: Construction

Est. Construction Cost: $5.4 million

Est. Construction Completion: Third Quarter of 2024

Sidewalk - Ella Boulevard from FM 2920 to Sapling Trail Court

Project Scope: Construct a sidewalk

Benefits: Improve pedestrian safety

Phase: Construction

Est. Construction Cost: $840,000

Est. Construction Completion: Fourth Quarter of 2024

Sidewalk Installation - Huffmeister

Project Scope: Install 1,750 linear feet of sidewalk

Benefits: Improve pedestrian safety

Phase: Construction

Est. Construction Cost: $356,000

Est. Construction Completion: Third Quarter of 2024

Sidewalk- Timberlane UD Partnership

Project Scope: Sidewalk and trail partnership with Timberlane UD and Breckenridge

Benefits: Improve connectivity and pedestrian safety

Phase: Construction

Est. Construction Cost: $1 million

Est. Construction Completion: Second Quarter of 2024

South Diamondhead Bridge Replacement (TxDOT)

Project Scope: Replacing the bridge

Benefits: Replacement of an existing bridge that has identified deficiencies

Phase: Construction

Est. Construction Cost: $5.5 million

Est. Construction Completion: Second Quarter of 2025

Stuebner Airline Bridge over Cypress Creek

Project Scope: Repair substandard construction of southbound departure lanes

Benefits: Improve road conditions

Phase: Construction

Est. Construction Cost: $900,000

Est. Construction Completion: Third Quarter of 2025

Subdivision Drainage Improvements- E132-00-00

Project Scope: Converting existing earthen channel to a concrete channel

Benefits: Increase conveyance and capacity of the channel to allow for adjacent recovery and resiliency projects

Phase: Construction

Est. Construction Cost: $22 million

Est. Construction Completion: Second Quarter of 2026

Telge Road Segment 4 - From North of Louetta to North of Telge Ranch Road

Project Scope: Convert a 2-lane road to a 4-lane concrete boulevard

Benefits: Increase traffic flow and safety

Phase: Construction

Est. Construction Cost: $15.1 million

Est. Construction Completion: Third Quarter of 2025

Tower Oaks Plaza Subdivision Drainage Improvements

Project Scope: Reconstruct asphalt roadways and upgrades to the drainage along Oak Plaza Drive, King Circle, Carla Way, Chavile, Lynn Haven Street, and Oak Plaza Drive

Benefits: To provide a smooth driving surface and improve drainage

Phase: Construction

Est. Construction Cost: $11 million

Est. Construction Completion: Fourth Quarter of 2024

Townsen Park-N-Ride Multimodal Connector

Project Scope: Construction of an 8-foot wide concrete hike and bike trail to connect the Townsen Park and Ride to the I-69 Historical Pedestrian Bridge Metro Park and Ride

Benefits: Trail connectivity to mass transportation options

Phase: Construction

Est. Construction Cost: $1.5 million

Est. Construction Completion: Third Quarter of 2025

Treaschwig Road, Segment 1A

Project Scope: Reconstruct from a 2-lane asphalt roadway to a 4-lane concrete blvd with storm sewer and sidewalk from west of Aldine-Westfield Rd to west of Cypress Creek

Benefits: Improved safety, increased capacity for vehicular travel, added safety and capacity for pedestrian mobility, and increased efficiency for drainage

Phase: Construction

Est. Construction Cost: $19.9 million

Est. Construction Completion: Second Quarter of 2026

Wallisville Road from west of Garth Road to west of North Main Street

Project Scope: Reconstruct from a 2-lane asphalt roadway to 4-lane concrete boulevard with storm sewer and sidewalk from Garth Road to Goose Creek Memorial High School.

Benefits: Improved safety, increase capacity for vehicular travel, added safety and pedestrian connectivity, and increased efficiency for drainage

Phase: Construction

Est. Construction Cost: $9.6 million

Est. Construction Completion: Second Quarter of 2025

West Lake Houston Parkway Sidewalk from Lakewood Pines Boulevard to Fintry Hills

Project Scope: Traffic signal rebuild

Benefits: Signal improvements

Phase: Construction

Est. Construction Cost: $162,500

Est. Construction Completion: Fourth Quarter of 2024

West Lake Houston Parkway Sidewalk from Summer Lake Ranch Drive to Lakewood Pines Boulevard

Project Scope: Construct sidewalk

Benefits: Improve pedestrian safety

Phase: Construction

Est. Construction Cost: $246,200

Est. Construction Completion: Fourth Quarter of 2024

West Lake Houston Parkway Sidewalk, Phase 1A

Project Scope: Construct sidewalk on both sides of West Lake Houston Parkway from Madera Run Parkway to Will Clayton Parkway

Benefits: Project will enhance pedestrian mobility in the area

Phase: Construction

Est. Construction Cost: $1.1 million

Est. Construction Completion: Fourth Quarter of 2024

Wortham Estates Subdivision Drainage Improvements

Project Scope: Installation of regional detention basin

Benefits: Reduce flood risk

Phase: Construction

Est. Construction Cost: $11.8 million

Est. Construction Completion: Third Quarter of 2025

Projects in Design

Asphalt Reconstruction 2024-4

Project Scope: Roadway improvements to Cypress Church, Penske, Malcomson

Benefits: Increasing safety and mobility throughout these areas

Phase: Design

Asphalt Reconstruction 2024-4: Old Town Spring

Project Scope: Reconstruct Old Town Spring area roadway

Benefits: Improving traffic flow and safety

Phase: Design

Barwood Subdivision Drainage Improvements

Project Scope: Subdivision drainage improvements and pavement reconstruction

Benefits: Increased drainage capacity, reduced flood risk, and reduced long-term maintenance costs

Phase: Design

Birnam Wood Boulevard, Segment 1

Project Scope: Construct remaining 2 lanes of a 4-lane concrete blvd with storm sewer and sidewalk from Hickory Gate Drive to south of the bridge over channel J109-01-01

Benefits: Improved safety, increased capacity for vehicular travel, added safety and capacity for pedestrian mobility, and increased efficiency for drainage

Phase: Design

Birnam Wood Boulevard, Segment 2

Project Scope: Construct remaining 2 lanes of a 4-lane concrete blvd with storm sewer and sidewalk between south of Otto Road to Cypresswood Drive

Benefits: Improved safety, increased capacity for vehicular travel, added safety and capacity for pedestrian mobility, and increased efficiency for drainage

Phase: Design

Boudreaux Road 3 - from Old Boudreaux Lane to west of Hufsmith-Kohrville Road

Project Scope: Convert 2-lane roadway to 4-lane to concrete boulevard

Benefits: Improved safety, increased capacity for vehicular travel, added safety and capacity for pedestrian mobility, and increased efficiency for drainage

Phase: Design

Copperfield Southdown Village Subdivision Drainage Improvements

Project Scope: Subdivision drainage improvements

Benefits: Increase drainage capacity, reducing flood risk

Phase: Design

Cutten Road from South of Bavaria Drive to Cossey Road

Project Scope: Construct 4-lane boulevard with bridge culvert

Benefits: Improving traffic flow and drainage

Phase: Design

Cypress Creek Estates Subdivision

Project Scope: Subdivision drainage improvements and pavement reconstruction

Benefits: Increased drainage capacity, reduced flood risk, and reduced long-term maintenance costs

Phase: Design

Cypress North Houston Road from Jones Road to Perry Road

Project Scope: Replace existing 2-lane asphalt road and roadside ditches with a 4-lane concrete boulevard with raised median and underground storm sewer system, including new or upgraded traffic signals at Autumn Mills Road, Misty Moss Lane, and Perry Road

Benefits: Better traffic throughout, less congestion, more functional drainage, and the clear safety improvements of converting to four lanes

Phase: Design

Cypresswood Drive at Cutten Road/Schroader Road

Project Scope: Traffic signal rebuild

Benefits: Signal improvements

Phase: Design

Cypresswood Drive at Purple Wisteria Drive

Project Scope: Installation of new mast arm traffic signal

Benefits: Improve driver safety

Phase: Design

Dowdell Woods Subdivision

Project Scope: Subdivision drainage improvements and pavement reconstruction

Benefits: Increased drainage capacity, reduced flood risk, and reduced long-term maintenance costs

Phase: Design

Edgewater Park

Project Scope: Design and construct new park that will include boat ramp, playgrounds, restrooms, and park facilities, park will also connect to the Spring Creek Greenway and the adjacent City of Houston Trail system

Benefits: Enhanced park amenities

Phase: Design

Forest Manor & Lake Houston Woodland Terrace Subdivisions

Project Scope: Subdivision drainage improvements

Benefits: Increased drainage capacity and reduced flood risk

Phase: Design

Gessner Road at Twelve Lakes Blvd/Loyel Pointe Drive

Project Scope: Installation of new mast arm traffic signal

Benefits: Improve driver safety

Phase: Design

Gosling Road at Hampton Pointe Boulevard Traffic Signal

Project Scope: Installation of new mast arm traffic signal

Benefits: Improve driver safety

Phase: Design

Gosling Road at West Rayford Traffic Signal

Project Scope: Modify existing signal with new mast arm traffic signal

Benefits: Improve driver safety

Phase: Design

Grant Road 3 from Telge Road to Shaw Road

Project Scope: Convert 2-lane roadway to 4-lane concrete boulevard

Benefits: Increase traffic flow and safety

Phase: Design

Highland Ridge and Highland Estates Subdivision Drainage Improvements

Project Scope: Subdivision drainage improvements

Benefits: Increase drainage capacity, reduce flood risk

Phase: Design

Hilshire Village Wirt Road Sidewalk - IH 10 to Westview

Project Scope: Install 3200 linear feet of sidewalk

Benefits: Improve pedestrian safety

Phase: Design

Huffmeister at Highway 6 Phase 2

Project Scope: Intersection improvements, southbound right turn lane

Benefits: Improve traffic safety

Phase: Design

Hufsmith Road Intersection Improvements

Project Scope: Intersection improvements to Hufsmith Road at Kuykendahl Road, Hufsmith Road at Stuebner Airline Road, and Hufsmith Road at Fm 2978

Benefits: Improve traffic safety

Phase: Design

Hufsmith-Kohrville Road 3b

Project Scope: Convert 2-lane to 4-lane concrete boulevard

Benefits: Improve traffic flow and safety

Phase: Design

Hufsmith-Kohrville Road, Segment 3A

Project Scope: Reconstruct from a 2-lane asphalt roadway to a 4-lane concrete blvd with storm sewer and sidewalk from north of Ezekiel Rd to north of Boudreaux Rd

Benefits: Improved safety, increased capacity for vehicular travel, added safety and capacity for pedestrian mobility, and increased efficiency for drainage

Phase: Design

Kolbe Road Drainage Improvements

Project Scope: Subdivision drainage improvements and pavement reconstruction

Benefits: Increased drainage capacity, reduced flood risk, and reduced long-term maintenance costs

Phase: Design

Kuykendahl Road at Alvin A. Klein Traffic Signal

Project Scope: Installation of new mast arm traffic signal

Benefits: Improve driver safety

Phase: Design

Kuykendahl Road at Cypressdale Drive Traffic Signal

Project Scope: Installation of new mast arm traffic signal

Benefits: Improve driver safety

Phase: Design

Louetta Road Pedestrian Flashing Signs, approximately 1,500 feet east of Telge Road

Project Scope: Installation of flashing signs

Benefits: Improve pedestrian safety

Phase: Design

N. Eldridge Parkway - Sidewalk

Project Scope: Construct sidewalk on both sides of the roadway from FM 529 to West Road and from West Road to 950' east of West Road

Benefits: Project will enhance pedestrian mobility in the area

Phase: Design

Norchester Subdivision Drainage Improvements

Project Scope: Subdivision drainage improvements

Benefits: Increase drainage capacity, reducing flood risk

Phase: Design

North Eldridge Parkway from Spring Cypress Road to Gregson Road

Project Scope: Replace existing 2-lane asphalt road and roadside ditches with a 4-lane concrete boulevard with raised median and underground storm sewer system, including a new traffic signal at Gregson Road and a study to determine if a traffic signal is warranted at Westlock Drive, sidewalks included along certain sections of the road project

Benefits: Better traffic throughout, less congestion, more functional drainage, and the clear safety improvements of converting to four lanes

Phase: Design

Piney Pointe Traffic Signals (3) - Phase 1

Project Scope: Replacing three traffic signals

Benefits: Signal improvements

Phase: Design

Shaw Road, Segment 2 - from Northpointe Boulevard to Boudreaux Road, Right of Way

Project Scope: Convert 2-lane roadway to 4-lane concrete boulevard

Benefits: Improve traffic flow and safety

Phase: Design

South Diamondhead Boulevard - from Sea Palms to Jib Boom Ct

Project Scope: Add 2 lanes to complete the full boulevard and construct the west-bound bridge

Benefits: Increase traffic capacity and improve safety

Phase: Design

Stuebner Airline Road at Five Forks Drive Traffic Signal

Project Scope: Installation of new mast arm traffic signal

Benefits: Improve driver safety

Phase: Design

Stuebner Airline Road at Hufsmith-Kuykendahl Road

Project Scope: Installation of new mast arm traffic signal

Benefits: Improve driver safety

Phase: Design

Stuebner Airline Road at Kleppel Road

Project Scope: Intersection Improvement

Benefits: Improve driver safety

Phase: Design

Telge Road Segment 5 - from North of Telge Ranch Road to North of Grant, Right of Way

Project Scope: Convert 2-lane road way to a 4-lane concrete boulevard

Benefits: Improve traffic flow and safety

Phase: Design

Timberlake Estates Subdivision

Project Scope: Subdivision drainage improvements and pavement reconstruction

Benefits: Increased drainage capacity, reduced flood risk, and reduced long-term maintenance costs

Phase: Design

Tower Oaks Meadows Subdivision Drainage Improvements

Project Scope: Subdivision drainage improvements and pavement reconstruction

Benefits: Increased drainage capacity, reduced flood risk, and reduced long-term maintenance costs

Phase: Design

Treaschwig Road, Segment A2

Project Scope: Reconstruct from a 2-lane asphalt roadway to a 4-lane concrete blvd with storm sewer and sidewalk, including a new bridge, from west of Cypress Creek to east of Birnam Wood Blvd

Benefits: Improved safety, increased capacity for vehicular travel, added safety and capacity for pedestrian mobility, and increased efficiency for drainage

Phase: Design

West Lake Houston Parkway - Sidewalk (Phase 2)

Project Scope: Construct sidewalk on West Lake Houston Parkway from Aerobic Drive to FM 1960

Benefits: Project will enhance pedestrian mobility in the area

Phase: Design

West Lake Houston Parkway at Firesign Drive

Project Scope: Traffic signal rebuild

Benefits: Signal improvements

Phase: Design

West Lake Houston Parkway at Kings River Drive/ Kings Lake Estates Boulevard

Project Scope: Traffic signal rebuild

Benefits: Signal improvemtns

Phase: Design

West Lake Houston Parkway at Lonesome Woods Trail

Project Scope: Traffic signal rebuild

Benefits: Signal improvements

Phase: Design

West Lake Houston Parkway at Pine Cup Drive

Project Scope: Traffic signal rebuild

Benefits: Signal improvements

Phase: Design

West Lake Houston Parkway at Upper Lake Drive

Project Scope: Traffic signal rebuild

Benefits: Signal improvements

Phase: Design

West Lake Houston Parkway – Sidewalk (Phase 1B)

Project Scope: Construct sidewalk on both sides of the roadway from Will Clayton Parkway to Aerobic Drive

Benefits: Project will enhance pedestrian mobility in the area

Phase: Design

West Rayford Road 1

Project Scope: Converting 2-lane roadway to 4-lane concrete boulevard from Kuykendahl Road to 400 feet east of Augusta Pines Parkway West

Benefits: Improving traffic flow and safety

Phase: Design

West Rayford Road 2

Project Scope: Converting 2-lane roadway to 4-lane concrete boulevard from 400 feet east of Augusta Pines Parkway West to Northcrest Drive

Benefits: Improving traffic flow and safety

Phase: Design

West Road at Bridge Park Dr Traffic Signal

Project Scope: Installation of new mast arm traffic signal

Benefits: Improve driver safety

Phase: Design

Will Clayton Parkway - Sidewalk

Project Scope: Construct sidewalk on Will Clayton Parkway from Tabor Brook Drive to Garbit Drive

Benefits: Project will enhance pedestrian mobility in the area

Phase: Design

Completed Projects

Apache Land Subdivision Drainage Improvement Project

Project Scope: Improvement to roadside ditches, replacing driveway culverts, and improving outfall

Benefits: Provides improved drainage throughout the subdivision to reduce flooding and improve road quality for safety

Estimated Construction Cost: $1.2M, HCED

Asphalt Reconstruction Package 2022-1 in the Cypress and Spring areas

Project Scope: Repaving of roads, new markings, and street signs along Tanner Road from Triway Lane to the Sam Houston Tollway, West Little York Road from North Eldridge Parkway to Brittmore Road, and Kuykendahl Road from north of Spring Cypress Road to north of 1960

Benefits: Increase safety and mobility throughout these areas

Estimated Construction Cost: $7.3 million

Atascocita Road, Blackstone Trails Drive Intersection Improvements

Project Scope: Install a new traffic signal at the intersection of Atascocita Road and Blackstone Trails

Benefits: Improve driver safety

Estimated Construction Cost: $370,000, HCED

Barker Cypress at Longenbaugh and Fry at Bridgeland Creek Parkway

Project Scope: Extend left turn lanes

Benefits: Improves traffic flow

Estimated Construction Cost: $150,000

Crosby Township/MUD (Burris) Subdivision Drainage Improvements

Project Scope: Provide improved drainage along 1st Street

Benefits: Reduce risk of flooding for homes along 1 st Street

Estimated Construction Cost: $100,000

Crosby Township/MUD (Franta) Subdivision Drainage Improvements

Project Scope: Remove brush and regrade ditch along the UPRR tracks

Benefits: Reduce risk of flooding along Franta Road, Werchan Street, and Miller-Wilson Road

Estimated Construction Cost: $100,000

Crosby-Lynchburg Road, Segment 3

Project Scope: 2-lane asphalt to a 5-lane (4 lanes with a continuous turn lane) concrete pavement between Magnolia Avenue and Lochness Drive

Benefits: Improves mobility between US-90 and IH-10

Estimated Construction Cost: $16,584,851

Crosby-Lynchburg Road, Segment 4

Project Scope: 2-lane asphalt to a 5-lane (4 lanes with a continuous turn lane) concrete pavement between Lochness Drive and Thorn Street

Benefits: Improves mobility between US-90 and IH-10

Estimated Construction Cost: $6,010,603

Cypress Creek Greenway Loops 1 & 2

Project Scope: Construct under crossings along Cypress Creek at Highway 249 (North and South Side) and construct pedestrian trails and boardwalks.

Benefits: Help connect portions of the Cypress Creek Greenway together and provide access to the Kickerillo-Mischer Preserve

Estimated Construction Cost: $3.7 million

Cypress Place Subdivision Asphalt Reconstruction

Project Scope: Reconstruct pavement throughout the Cypress Place Subdivision

Benefits: Improved safety and reduced long-term maintenance costs

Estimated Construction Cost: $1.1 million

Cypress Place Subdivision, Phase 2

Project Scope: Subdivision drainage improvements

Benefits: Increased drainage capacity and reduced flood risk

Estimated Construction Cost: $2.1 million

Cypresswood Drive, west of Glen Way Drive

Project Scope: Install pedestrian flashing signs and sidewalk

Benefits: Improve driver safety

Estimated Construction Cost: $50,000

Ella Boulevard/Falvel Road - Sidewalk

Project Scope: Construct new sidewalk from 420 feet south of Spring Cypress Road to FM 2920 and reconstruction of sidewalk along the eastside from Sapling Trail Court to Spring Cypress Road

Benefits: Project will enhance pedestrian mobility in the area

Estimated Construction Cost: $900,000

Flashing School Zone - Phase II

Project Scope: Construction of new school zone flashers for schools in Cy-Fair ISD

Benefits: Provides increased safety elements within the school zone

Estimated Construction Cost: $1.1M

Flashing School Zone, Phase III – Spring/Humble/Crosby

Project Scope: Install flashing school zone lights

Benefits: Brings more attention to school zone rules for the safety of pedestrians in school zones

Estimated Construction Cost:

Forest Shadows Subdivision

Project Scope: Subdivision drainage improvements through construction of a detention basin, culvert replacements, ditch regrading, and limited pavement reconstruction

Benefits: Improved safety and increased efficiency for drainage

Estimated Construction Cost: $3.4 million

Foxwood Subdivision Drainage Improvements

Project Scope: Convert 2-lanes to a 4-lane boulevard

Benefits: Provide improved drainage throughout the subdivision and road quality for safety.

Estimated Construction Cost: $310,000

Garth Road - Sidewalk

Project Scope: Construct sidewalk on both sides of the roadway from Seabird Street to Wallisville Road

Benefits: Project will enhance pedestrian mobility in the area

Estimated Construction Cost: $837,000

George H.W. Bush Community Center

Project Scope: Construction of a new 2-story community center next to Cypresswood Drive

Benefits: Provide community with a center that will include multiple classrooms, gathering spaces, as well as a large community hall that will be reservable by the public

Estimated Construction Cost: $5.4 million

Gosling Road Bridge over Spring Creek

Project Scope: 2,100' long concrete twin bridge to tie into the 4-lane concrete boulevard to the north and south

Benefits: Improve safety and traffic flow by providing 2 lanes for southbound traffic and completing the mobility connection between Harris and Montgomery Counties

Estimated Construction Cost: $9,377,674

Gosling Road, Segment 3

Project Scope: Convert 2-lanes to a 4-lane boulevard

Benefits: Improve safety and traffic flow by providing 2 lanes for northbound traffic and 2 lanes for southbound traffic with a raised median in between.

Estimated Construction Cost: $7,412,076

Greenhouse Road Segment 4 from Toledo Bend Trails Lane to south of Tuckerton Road

Project Scope: Construct the remaining two lanes of a 4-lane concrete boulevard including a twin bridge

Benefits: Includes an increased capacity for traffic volume, a safer roadway, and improved drainage

Estimated Construction Cost: $2,241,445

Greenhouse Road Segment 5 from Cornerstone Arbor Drive to south of Cypress North Houston Road

Project Scope: Construct the remaining two lanes of a 4-lane concrete boulevard including a traffic signal at Towne Lake Parkway

Benefits: Includes an increased capacity for traffic volume, a safer roadway, and improved drainage.

Estimated Construction Cost: $3,544,680

Greenhouse Road Segment 6 from north of Cypress North Houston Road to Cypress Creek

Project Scope: Construct the remaining two lanes of a 4-lane concrete boulevard

Benefits: Includes an increased capacity for traffic volume, a safer roadway, and improved drainage

Estimated Construction Cost: $1,799,666

Greenhouse and Mound Roadway Improvements

Project Scope: Convert 2 lane roadway to 4 lane concrete boulevard

Benefits: Improve traffic flow and safety

Estimated Construction Cost: $1.4 million

Hemwick Subdivision Roadway Reconstruction

Project Scope: Reconstruct local roadways within the Hemwick subdivision (Hemwick Drive, Deval Drive, Florafield Lane, Ladino Run, Gentry Road, McCaney Drive, and Aspen Lane) to meet current Harris County standards

Benefits: Will improve roadway conditions and safety as well as improve localized drainage within the subdivision

Estimated Construction Cost: $3.6 million

Holderrieth Road, Segment 2

Project Scope: Reconstruct 2-lane asphalt roadway to 4-lane concrete boulevard with storm sewer

Benefits: Improved safety, increased capacity for vehicular travel, added safety and capacity for pedestrian mobility, and increased efficiency for drainage

Estimated Construction Cost: $31.2 million

Huffmeister at Highway 6 Phase 1

Project Scope: Intersection improvements, southbound dual left turn lane

Benefits: Improve traffic safety

Estimated Construction Cost: $150,000

Jones Road at Charles Road Traffic Signal

Project Scope: Construction of a new mast-arm traffic signal with related pedestrian facilities

Benefits: Improved driver safety

Construction Cost: $470,000

Kuykendahl Road Repaving

Project Scope: Repave Kuykendahl Road between north of Spring Cypress Road and north of FM 1960. Project will include asphalt reconstruction, new markings and street signs along the road segment.

Benefits: Increase safety and mobility

Estimated Construction Cost: $4 million

Kuykendahl at Creekside Green Drive Intersection Improvement

Project Scope: Modifying the northbound and southbound left turn lane and rebuild traffic signal

Benefits: Improves driver’s visibility of pedestrians, bringing the intersection to be consistent with other signalized intersections in the area

Estimated Construction Cost: $800,000

Lynwood Estates Subdivision Drainage Improvements

Project Scope: Provide improved drainage throughout the subdivision and road quality for safety

Benefits: Reduce risk of flooding throughout subdivision

Estimated Construction Cost: $2.8 million

Madera Run Parkway from Radura Road to Hickory Arroyo Drive

Project Scope: Construct the remaining 2 lanes of a 4-lane concrete boulevard between Radura Road and Hickory Arroyo Drive through a partnership with Harris County MUD 504

Benefits: Improved safety and increased capacity for vehicular travel

Estimated Construction Cost: $1.2 million

Mason Road at Cypresswood Drive Intersection Improvements

Project Scope: Construction of dual left turn lanes on the southbound approach, extending other left turn lanes as needed, and modifying the traffic signal to accommodate the lane additions

Benefits: Improved driver safety

Estimated Construction Cost: $415,000

Mercer Visitor Center

Project Scope: Reconstruction of the visitor center located at Mercer Park that was damaged from previous flood events

Benefits: Provide park users a place to have programs and events to help enhance their park experiences

Estimated Construction Cost: $700,000

Mossy Oaks Subdivision Asphalt Reconstruction

Project Scope: Reconstruct 2-lane asphalt roads

Benefits: New pavement improves aesthetics, increases driver safety, and reduces maintenance costs

Estimated Construction Cost: $1,691,471

North Eldridge Parkway at Fetlock Drive Traffic Signal

Project Scope: Construction of a new mast-arm traffic signal with related pedestrian facilities

Benefits: Improved driver safety

Estimated Construction Cost: $360,000

Northlake Forest Subdivision Drainage Improvements

Project Scope: Provide improved drainage throughout the subdivision and road quality for safety

Benefits: Reduce risk of flooding throughout subdivision

Estimated Construction Cost: $640,000

Plum Grove Road in Huffman

Project Scope: Adding a westbound right turn lane and traffic signal along the portion of Plum Grove Road that turns onto FM 2100

Benefits: Decrease traffic accidents and improve traffic flow along both roads

Estimated Construction Cost: $330,000

Prestonwood Forest Subdivision Drainage Improvements

Project Scope: Provide improved drainage along Hargrave Road and BNSF railroad ditch

Benefits: Reduce risk of flooding within the southern end of the subdivision

Estimated Construction Cost: $880,000

Riley Chambers Parking Lot improvements

Project Scope: Reconstruct the parking lot near football field

Benefits: Improve area for visitor parking

Estimated Construction Cost: $250,000

Sandpiper Village Subdivision

Project Scope: Subdivision drainage improvements and limited pavement replacement

Benefits: Increased drainage capacity and reduced flood risk

Estimated Construction Cost: $5.6 million

Sandpiper Village Subdivision

Project Scope: Subdivision drainage improvements and limited pavement replacement

Benefits: Increased drainage capacity and reduced flood risk

Estimated Construction Cost: $5.6 million

Schiel Road Segment 1 from east of SH-99 to west of Fairfield Place Drive

Project Scope: Convert 2-lane asphalt with roadside ditch to a 4-lane concrete boulevard with raised median and underground storm sewer

Benefits: Increased capacity for traffic volume, a safer roadway, and improved drainage

Estimated Construction Cost: $4.8 million

Sidewalk Package 1, Phase III

Project Scope: Construction of 5’-wide sidewalks on Queenston Boulevard in Cy-Fair ISD close to Birkes Elementary and Aragon Middle Schools.

Benefits: Improve safety of pedestrians along walkways

Estimated Construction Cost: $175,000

Spring Cypress at Trail Cypress Blvd

Project Scope: Install new traffic signal

Benefits: Improves traffic safety

Estimated Construction Cost: $400,000

TC Jester from Winding Ridge to Bur Oak

Project Scope: Install flashing lights and sidewalk

Benefits: Improve pedestrian safety

Estimated Construction Cost: $120,000

Tall Pines Subdivision Asphalt and Drainage Improvement Project

Project Scope: Reconstruct asphalt roadways and upgrades to the drainage. Pine Drive, Willow Lane, Aspen Drive, Elm Drive, Dogwood Lane, Red Bud Lane, Mimosa Lane, and Cottonwood Lane have all been reconstructed with improved drainage and culverts.

Benefits: To provide a smooth driving surface and improve drainage

Estimated Construction Cost: $3.7 million

Telge Road Reconstruction -Phase 1 from Tuckerton Drive to Moray View Drive

Project Scope: Reconstruct existing 4-lane concrete roadway, driveway reconstruction and new roadway signage.

Benefits: Increase roadway safety

Estimated Construction Cost: $2 million

Telge Road Reconstruction – Phase 2 from Moray View Drive Drive to Wyman Gordon Way

Project Scope: Reconstruct existing 4-lane concrete roadway, driveway reconstruction and new roadway signage

Benefits: Increase roadway safety

Estimated Construction Cost: $2.6 million

Telge at 290

Project Scope: Intersection improvements to southbound right turn lane and left turn lane

Benefits: Improve traffic flow and safety

Estimated Construction Cost: $756,000

Temporary Traffic Signal - Telge at Boudreaux

Project Scope: Temporary traffic signal & turn lanes

Benefits: Improve traffic safety

Estimated Construction Cost: $1.3 million

Timber Forest Drive Bridge over UPRR

Project Scope: New 4-lane bridge over the UPRR tracks

Benefits: Improves safety with an elevated RR crossing and provides a second north-south corridor for residents

Estimated Construction Cost: $6,667,000

Uptown Development Wilson Gully Repairs

Project Scope: Drainage Improvements

Benefits: Increased efficiency for drainage

Estimated Construction Cost: $6.8 million

Waynewood Subdivision Asphalt Project

Project Scope: Repair the asphalt roadway and provide new markings and street signs along Pinedell Drive, Ladina Run Street, and Charolais Drive

Benefits: To provide a smooth driving surface and increase safety

Estimated Construction Cost: $824,910

West Cypress Forest Drive at Cypresswood Drive

Project Scope: Box culvert extensions and ditch regrading

Benefits: Increased safety and improved maintenance

Estimated Construction Cost: $263,000

West Road at Windhaven Lakes/Lone Star College Driveway

Project Scope: Install new traffic signal

Benefits: Improves traffic safety

Estimated Construction Cost: $350,000

Western Trails Subdivision Pavement Repair Sidewalk

Project Scope: Reconstruct local subdivision roadways

Benefits: Roads will be reconstructed and provide a smooth driving surface that will also enhance safety

Estimated Construction Cost: $1.3 million

Westgate Subdivision Asphalt and Drainage Improvement Project

Project Scope: Reconstruct asphalt roadways and upgrades to the drainage. Vernon Road, Westover Road, Westgate Road, and Jasper Lane have all been reconstructed with improved drainage and culverts.

Benefits: To provide a smooth driving surface and improve drainage

Estimated Construction Cost: $2 million